This design/build installation of a 25'x72' acoustical sound enclosure included six 42'x10' high sound rated windows, two high speed roll up doors, extensive HVAC, electrical and sprinkler modifications and exhaust units servicing the sound enclosure and equipment pits.  

Installation of two new dock doors required removal of existing pre-cast concrete steps. man door and excavation to make way for the new concrete truck apron. Openings were cut into the building for a new man door & dock doors.  A new 20'x60' concrete truck apron was installed & doweled into the existing concrete apron along with a new retaining wall and stairs.  New dock levelers, lights & shelters were installed to complete the project.  All work was completed while the facility maintained operations.